SolutionsManufacturing · Optimisation

More parts in every furnace load

Danfoss

Software that plans how to load industrial furnaces so that more parts fit in each load. The furnace is the slowest step in the factory, so every extra part in it means more output.

  • 20 furnacesPlanned 14 days ahead
  • Every dayA new plan
  • 3DWhich parts go in, and how they are stacked
  • YearsIn production

In short

For
Factories where one expensive machine sets the pace
The problem
The most expensive machine runs below capacity.
What it does
A ready plan every day that fits more parts into each load.
Status
In use for several years

Who it is for

For factories where one expensive machine sets the pace

The problems it solves

  1. The most expensive machine runs below capacity.

  2. Loads are planned by hand by people who are hard to replace.

  3. Every load is a 3D puzzle with many rules.

Built for
  • Manufacturers running furnaces, ovens or batch processes
  • Plants where the expensive machine is the bottleneck
  • Anyone packing parts, pallets or batches by hand

How it works

How the software plans each furnace load

Parts are heated in large vacuum furnaces, many at once, stacked in layers. Deciding which parts go together, and how to stack them, is a 3D puzzle with many rules. The software solves the puzzle every day and gives the operators a ready plan.

  1. Learn the factory’s rules

    Furnace size, which parts can be heated together, what is needed next.

  2. Plan from real orders

    The planners compare the first plans with their own until they trust them.

  3. Use it every day

    Operators get a new plan daily; unusual cases still go to a person.

  4. Use it for other jobs

    The same software now also plans other ovens and pallet loading.

The load from the system, stacked layer by layer in 3D — drag to turn it

What changed

Before and after

Before

Experienced planners built each furnace load by hand, and space was lost every cycle.

After

A ready plan every day that fits more parts into each load.

Client
Danfoss
Plans
20 furnaces, 14 days ahead
Also used for
Other ovens and pallet loading
Status
In use for several years

Talk to an engineer

30 minutes about your case, with the engineers who built this. No slides.